1 |
Construction of Main Gate House at Cyberpark, Kozhikode- Work completed in November 2022 |
2 |
Construction of Covered car parking area and Rest rooms at Cyberpark Park Centre- Work completed in January 2023 |
3 |
Internal Road construction works- Work is almost completed except a small stretch where Neighbors demanding access to the proposed road near the temple located in the Campus of Cyberpark. |
4 |
compound wall construction. Work is almost completed except a small stretch where neighbors demanding access to the proposed road near the temple located in the campus of Cyberpark |
5 |
Recreational facilities at Cyberpark, Kozhikode-Work is in progress, expected to be completed in the financial year 2023-24 |